HIGHWAY 289 ROADWORK UPDATE: According to the Arkansas State Highway and Transportation Department as of today (Oct. 18), the roadwork being done to State Highway 289 is well on its way to being complete. Tuesday’s work consists of finishing setting boxes; Wednesday’s work involves backfilling: setting stones around the boxes, taking the dirt away that has been used for turn-arounds, and bringing the road back up to grade. Weather permitting, crews may be done with roadwork by Friday, but could be as late as Monday, Oct. 24. This section of 289 will remain gravel until it settles, then the road will be paved. Photo/Karen Sherrell

detour3
by Carrie Johnson
Repairs to a drainage system will require the closure of a section of State Highway 289 between Horseshoe Bend and Glencoe, according to Arkansas State Highway and Transportation Department, AHTD, officials. The closure will begin on Monday, October 10 at 8 a.m.
The work will require closure of 289 between State Highway 354 and U.S. Highway 62. Motorists traveling on 289 will follow a detour. This is the most direct route to 62 from Horseshoe Bend, so allow yourself plenty of extra time for traveling.
Routes around the roadwork that include only highway are Highway 354 to Oxford, then right on Highway 9 to Salem or left on 9 to Melbourne; or 289 to Peace Valley Road, then left on Highway 167 to Ash Flat or right on 167 to Batesville. Local traffic should consider alternate routes between 354 and 62, also known as dirtroads.
There will be warning signs at the Glencoe turn off 62 and at the four-way in Horseshoe Bend alerting drivers of the roadwork ahead. A barricade will be in place at Morriston Fire Department.
All students that ride the bus that live beyond the closure will be picked up at Hillbilly U-Pump in Glencoe at 7:30 a.m. and dropped off at approximately 3:20 p.m. For those that are still unaware of where the line is drawn, if your child is usually picked up at The Quilted Heart and beyond (towards Horseshoe Bend), expect to have to find a different route. Your child’s bus and bus driver will remain the same; all parents of affected students should have received a letter from the Salem School District Superintendent Wayne Guiltner notifying route changes.
The closure will conclude on Friday, October 21 at 5 p.m., weather permitting. The District Maintenance Crew will finish the section of 289 that lacks super pave when the repair is complete. Drivers should exercise caution when approaching and traveling through all highway work zones. Additional travel information can be found at IDriveArkansas.com.

stop
by Carrie Johnson
In addition to the roadwork that State Highway 289 received recently, drivers need to be on the look out for more roadwork in the upcoming weeks. Repairs to two separate drainage systems in the area require closures to sections of state highways.
On Monday, September 12 at 8 a.m., a closure on a section of State Highway 58 north of Poughkeepsie and just outside of Williford in Sharp County began, according to Arkansas State Highway and Transportation Department, AHTD, officials. The work requires closure of 58 between State Highway 354 and U.S. Highway 63. Motorists traveling on 58 will follow a detour. The northbound detour route is 354 north to U.S. Highway 167 and then U.S. Highway 62 east to 63. The southbound detour route is 63 west to 62 and then 167 south to 354. Weather permitting, roadwork will conclude on Friday, September 30 at 5 p.m.
Directly following the drainage system repair at Williford, the crew will relocate to State Highway 289 between Glencoe in Fulton County and Horseshoe Bend in Izard County. The repair, weather permitting, is expected to begin in early October. Once the drainage system is done, the District Maintenance Crew will finish the section of 289 that lacks the super pave.
This work also requires a road closure between Horseshoe Bend and Glencoe. This is the most direct route to 62; motorists will have to find an alternate route. A press release with updated information such as detour routes will be published closer to the date of the repair.
Drivers should exercise caution when approaching and traveling through all highway work zones. Additional travel information can be found at IDriveArkansas.com or ArkansasHighways.com. You can also follow AHTD on Twitter @AHTD.